It's often said that failing to plan is planning to fail and
this statement couldn't ring more truth in an activity of this magnitude as we
set forth to build a very good shelter for Handicap Solidaire Burkina -
International Service partner's organisation. Having achieved our objective by
realising this activity, we have found it appropriate given the cooperative
feelings and attitude among our team to share a blueprint of how
to build a shelter in 10 fundamental steps with the world.
1 / Planning and Evaluation of Risks:
Risk assessment Evaluation des risques |
2 / Architecture:
Undoubtedly, a very challenging
step in the quest to build a shelter, asserting an architectural authority on
the construction of the shelter is quintessential for the realisation of the
project. This stage provides builders a physical representation of the shelter
in terms of structure, shape and design. Moreover, it also paves the way for an
effective analysis of the external factors which will be affected or
instrumental during and after the construction of the shelter.
3 / The Material:
After taking all design and
architectural aspects into account, the next step is to ensure all raw
materials needed to put the pieces together are your disposal. You could have
the grandest of architectural design but
not having the right materials would put a dent on the prospects of realising
your objectives. In our case, some of the materials we needed for this project
included some woods, chains, cement, stones, water and a roof made out of dry
herbs.
4 /
Execution of measurements:
As previously mentioned in the
'architectural' stage, a practical measurement of the physical environment will
have to be conducted before proceedings on the field begins. The importance of
this exercise must not be undermined as it gives builders a sense of direction
and understanding of the spaces and ascertains that the positions of the
planted woods are parallel to each other. Failure to do so can make the best
architectural design go from order to disorder, with planted woods and holes
not having the same distance between them.
![]() |
Digging holes creusage ses trous |
5 /
Wood Cutting:
This exercise is highly
recommended for the purpose of ensuring that the woods planted in the ground
coincide conveniently with the woods used to maintain the roof. This requires
the latter to be tailored adequately in order to create a transversal line that
connects with the posts planted deep in the ground. In addition, this wood also
needs to be long and light in weight to ensure that it doesn't weight very
heavily on the posts. Ideally, the posts must be very robust and solid as they
will be key in assuring the reliability and durability of the shelter.
6 /
Establishment of the posts:
This is a very important in the
construction of the shelter and is to do with solidifying the posts in the bid
to ascertain the reliability and durability of the shelter. Failure to solidify
the posts could lead to the shelter being unable to remain stable against
severe weather conditions such as winds and rains. So how are the posts
solidified? First, the holes must be filled with plenty of stones after the
posts have been planted. Next, the holes must be entirely filled with cements
and water will have to be sprinkled two times a day, over a period of three
days in order to reinforce the stronghold of the posts.
7 / Deposit of wood on each
post:
Deposite of wood Depot des transversaux |
8 /
Placing the roof:
This step will once again require
the collective to work together to put the roof on top of the posts and
transversals. A medium-sized roof needs to placed in different sections of the
shelter and may appear to be in disorderly fashion at first but the next step
will allow you to bring order by attaching them to the woods on which they have
been laid upon.
9 / The attachment phase:
Attachement Attacher le bois |
Attachment |
10 / The application of oil drain and last final improvements:
It is highly necessary to paint
wood with an oil drain to avoid any attack from ants and termites. In addition,
it is also highly recommended to revise the project plan to make sure that
nothing has been forgotten and that all construction objectives have been met.
An all clear from the building managers will bring this activity to a close and
a well constrcuted shelter that pleases the eyes.
LES 10 VOIES NECESSAIRES POUR
UN BON HANGAR
Aucune œuvre humaine n’est réussie
sans organisation. Il va s’en
dire donc que même pour la réalisation
de votre hangar il faudra au préalable
planifier, conceptualiser, se donner les moyens pratiques de réalisation. Nous
avons vécu l’expérience et nous aimerions vous la partager à travers ces « 10 Etapes Essentielles pour
construire un Hangar ».
2/ Architecturer: Cette étape
est très importante dans la mesure où il s’agit ici de donner une structure a
votre Hangar; c’est à dire
concevoir et transformer des espaces extérieurs selon des critères esthétiques
et des règles sociales, techniques, économiques, environnementales. C’est là qu’il faut faire des mesures théoriques. Cependant que faut-il pour matérialiser cette réalisation?
3/Réunir le matériau : C’est la matière que l’on peut collecter puis
façonner pour fabriquer ou construire le hangar.
Autrement dit, c’est rassembler tous les
éléments
constitutifs qu’il faut. D’ailleurs, il faut des bois pour les poteaux et les
transversaux, une machette ou coupe-coupe, une barre à mine, une pioche, des chaines, des pointes en
acier, un fil de fer, des seccos, du
ciment, des cailloux et de l’eau.
4/ Dimensionner votre hangar :
Il est très important de mesurer les dimensions de votre hangar (longueur,
largeur, hauteur et même la profondeur des trous à creuser). Cette étape est
très importante dans la mesure où un simple centimètre de trop ou de moins peut
affecter la structure finale de votre hangar et par conséquent vous aurez à
faire recours à votre capacité d’improvisation afin de corriger les erreurs. Ce
qui rend le travail plus laborieux et moins efficace. La profondeur des trous
doit être
au moins de 45 CM.
au moins de 45 CM.
5/
Tailler le bois: Il s’agit ici
d’identifier et tailler le bois qui va servir de support ou poteaux et les
transversaux. Le bois de poteaux doit être robuste et solide afin de supporter
le poids de votre hangar d’une part et l’effet du temps de l’autre. La solidité
et la durabilité de votre hangar dépendent de ce bois. Les transversaux doivent
être assez long, solide et légers à la fois pour ne pas trop peser sur le
hangar.
6/
Planter les poteaux: Cette étape est
aussi très importante et à prendre très au sérieux car si les poteaux ne sont
pas solidement plantes, votre hangar ne sera pas assez solide et va beaucoup
basculer sous le vent. Les poteaux doivent être plantés et soutenus par des
cailloux. Vous pouvez aussi couler du béton
afin d’augmenter sa solidité. Il
faudra s’assurer d’arroser le béton matins et soir pendant au moins deux jours
pour améliorer sa consistance et sa durabilité. Laisser alors les poteaux
plantes pendant deux jours avant de monter la toiture.
7/
Déposer les transversaux sur les poteaux:
Sur chaque poteau, déposer un transversal pour rejoindre le poteau symétriquement
opposé. A l’aide d’une chaine, attacher le transversal au poteau. La chaine est
utilisée pour sa solidité et sa flexibilité. Il faudra toujours soutenir les
poteau a cette étape pour ne pas affaiblir le béton.
10/ Prendre des précautions anti
termites : Asperger le toit et les poteaux avec de l’huile de vidange
ou toute autre solution permettant de
tenir les insectes (termites) loin du hangar. Il faudra aussi faire les retouches pour s’assurer qu’aucun détail
n’a été oublié et que tout est parfait.